For your information and comment I am including the current installation
schedule as outlined in the contract MU has with NEC.
===========================================================================
NETWORK INSTALLATION AND PERFORMANCE SCHEDULE
Phase 1: Hubs and priority buildings
Start: November 1, 1995
Completion: August 15, 1996
Buildings to include at least, but not limited to, in order of priority;
Bachelor Hall (East Quad)
Benton Hall (North Quad)
Gaskill Hall (Central Quad)
Harrison Hall (Central Quad)
Hughes Hall Including the Brill Science Library (Central Quad)
King Library (Central Quad)
Kreger Hall (Central Quad)
Phillips Hall (South Quad)
Shideler Hall (Central Quad)
Installation is to include all relevant (as designed)
Ethernet transmission equipment, and all work required
at the station level (voice, data, video jacks and cabling).
Video electronics may not necessarily work at time of building
completion during this phase. Network Operating Center
software and hardware are to be included
Phase 2: Outside plant to hub buildings
Start: November 1, 1995
Completion: October 31, 1996
Buildings to include:
Brandon Hall
Campus Avenue Building
Dorsey Hall
Hoyt Hall
Hughes Hall
Johnston Hall (Middletown)
King Library
Macracken Hall
Mosler Hall (Hamilton)
Shriver Center
Tappan Hall
Upham Hall
Installation is to include all outside plant to Hub Buildings.
Phase 3: Distance learning classrooms
Start: November 1, 1995
Completion:August 15, 1996
Buildings to include:
Gaskill Hall (Oxford)
Theskin Hall (Middletown)
Phelps Hall (Hamilton)
Installation is to include distance learning classrooms
installed on Hamilton, Middletown, and Oxford campuses.
Phase 4: Fourteen upper class residence buildings
Start: November 1, 1995
Completion: August 15, 1996
Buildings to include:
Bishop Hall
Brandon Hall
Elliott Hall
Flower Hall
Hahne Hall
Hamilton Hall
Hepburn Hall
MacCracken Hall
Martin Dining Hall
McFarland Hall
Ogden Hall
Richard Hall
Stoddard Hall
Swing Hall
Installation is to complete work in upper class residence
halls in North, Central and South Quads.
Phase 5: Video systems external to buildings
Start: February 1, 1996
Completion:August 15, 1996
Installation is to include the video infrastucture with
all video transmission equipment required, together with
video head end and satellite antenna installations. Video
infrastructure is defined as those portions of equipment
which exist external to the actual end point buildings.
Phase 6: Initial hot hubs
Start: November 1, 1995
Completion: August 15, 1996
Buildings to include:
Brandon Hall
Hoyt Hall
Hughes Hall
King Library
Macracken Hall
Tappan Hall
Upham Hall
Installation is to include providing, in seven (7) out of the
twelve (12) hubs, the ability to connect an Ethernet device to
the hub and maintain an 100 mb/s path to the main network at
the end of the phase. Each hub shall have the capability of
receiving two (2), 80 channel broad band video services from the
head end. (One academic/administrative Service, and one
entertainment service.) Optical fiber shall be terminated in
order to receive the portable reverse feeds from all buildings.
Phase 7: Complete hot hubs
Start: August 16, 1996
Completion: August 15, 1997
Buildings to include:
Campus Avenue Building
Dorsey Hall
Johnston Hall (Middletown)
Mosler Hall (Hamilton)
Shriver Cemter
Installation is to include completing the remaining five (5)
hubs as per the definition in Phase 6. Each hub shall have
the capability of receiving two (2), 80 channel broad band
video services from the head end. (One academic /administrative
Service, and one entertainment service.) Optical fiber shall
be terminated in order to receive the portable reverse feeds
from all buildings.
Phase 8: All external work completed
Start: August 16, 1996
Completion: August 15, 1997
Installation is to include completion of all other remaining
external work. This completes all trenching, construction, etc.
outside of the actual buildings.
Phase 9: Residence hall completion
Start: August 16, 1996
Completion: August 15, 1997
Buildings to include:
Alexander Dining Hall
Anderson Hall
Clawson Hall
Collins Hall
Dennison Hall
Dorsey Hall
Emerson Hall
Erickson Hall
Harris Dining Hall
Havighurst Hall
Mary Lyon Hall
McBride Hall
Miami Manor (A, B, C & D)
Minnich Hall
Morris Hall
Peabody Hall
Porter Hall
Reid Hall
Scott Hall
Stanton Hall
Symmes Hall
Tappan Hall
Thomson Hall
Wilson Hall
Installation is to include competion of installation in all
residence halls. Completion is defined as all buildings
"jacked" and hot for both Ethernet systems and cable TV.
Phase 10: External communications, security, and address administration
Start: December 1, 1995
Completion: August 1, 1996
Installation is to include:
a)The modem pool (300 modems)
Start: December 1, 1995
Completion: August 1, 1996
b)Access security and address administration verification
Start: December 1, 1995
Completion: August 1, 1996
c)Any pertinent T-1 connections to external data
communications equipment.
Phase 11: Remote campuses
Start: September 1, 1996
Completion: April 1, 1997
Buildings to include:
Hamilton Conference Center
Hamilton Gymnasium
Mosler Hall
Phelps Hall and Parrish Auditorium
Rentschler Library
Finkelman Auditorium
Gardner Harvey Library
Johnston Hall
Middletown Gymnasium
Regional Book Depository
Thesken Hall
Verity Lodge
Installation to include completion of all regional campus
locations. Video systems will be installed as per University
Technical Officer/NEC design specification.
Phase 12: Remaining buildings
Start: April 1, 1997
Completion: July 30, 1998
Buildings to include:
Alumni Hall
Art Building
Art Museum
Billings Natatorium (Gymnasium)
Pearson Hall (Bio Sciences)
Bonham house
Boyd Hall
Campus Avenue Building
Center for Performing Arts
Central Food Stores
Cole Service Building
Cook Place
Culler Hall
Dodds Hall
East End
Edwards House
Goggin Ice Arena
Grey Gables (formerly Glos)
Hall Auditorium
Hanna House
Health Services Center
Hiestand Hall,
Hoyt Hall
Irvin Hall
Joyner House
Kelley House
Kumler Chapel
Langstroth Hall
Laws Hall
Lewis Place
MacMillan Hall
Marcum Conference Center
Mayer House
McGuffey Hall
McKee Hall
Miami Inn
Millet Assembly Hall
Morris House
Murstein Alumni Center
Old Manse
Oxford College
Patterson Place
Power Plant
Presser Hall
Recreational Sports Center
Robertson Hall
Roudebush Hall
Rowan Hall
Sesquicentennial Chapel
Shriver Center
Simpson Guest House
South Campus Refrigeration Plant
Upham Hall
Warfield Hall
Wells Hall
Western Lodge
Western Maintenance Buildings
Williams Hall
Withrow Court
Yager Stadium
Installation to include completion of remaining buldings
in their entirety. Completion includes all data and video
systems as per University Technical Officer/NEC design
specification.
Phase 13: Testing and acceptance.
Start: August 1, 1998
Completion: November 1, 1998
Work to include final testing and acceptance of all systems.
Agreement - Data and Video Network Installation Miami University
and NEC Business Communication Systems (East)
|